Appendix 1: Playground Refurbishment Programme and new play and fitness provision
Table 1: completed sites |
|||
Site |
Spend |
Funded by |
Status |
Barn Rise |
£60,000 |
Section 106 |
Completed |
Bexhill Road |
£78,000 |
Housing |
Completed |
Blakers Park |
£100,000 |
Section 106 & City Parks Capital |
Completed |
Carden Park |
£440,000 |
Section 106 |
Completed |
Chalk Pit |
£60,000 |
Section 106 |
Completed |
Dyke Road |
£50,000 |
Section 106 |
Completed |
East Brighton |
£45,000 |
Section 106 |
Completed |
East Hill |
£83,500 |
Section 106 |
Completed |
Greenleas Park |
£50,000 |
Section 106 |
Completed |
Haig Avenue |
£50,000 |
Housing |
Completed |
Hangleton Park |
£80,000 |
Section 106 & City Parks Capital |
Completed |
Hodshrove Road |
£130,000 |
Housing |
Completed |
Hollingdean Park |
£308,000 |
Section 106 & Housing |
Completed |
Hove Park |
£142,000 |
Section 106 |
Completed |
Knoll Park |
£80,000 |
Section 106 & City Parks Capital |
Completed |
Mackie Park |
£80,000 |
City Parks Capital |
Completed |
Middle Park |
£130,000 |
Section 106 |
Completed |
Preston Park |
£100,000 |
Parking income |
Completed |
Queens Park |
£146,000 |
Section 106 |
Completed |
Rottingdean |
£30,000 |
Section 106 |
Completed |
Saltdean Oval |
£50,000 |
Section 106 |
Completed |
Saunders Park |
£50,000 |
Section 106 |
Completed |
St Ann’s Well Gardens |
£50,000 |
Section 106 |
Completed |
St Nicholas |
£120,000 |
Section 106 |
Completed |
Stoneham Park |
£45,000 |
Section 106 |
Completed |
Tarner Park |
£60,000 |
Section 106 |
Completed |
Vale Park |
£45,000 |
Section 106 |
Completed |
Victoria Rec Road |
£45,000 |
Section 106 |
Completed |
Whitehawk Way |
£85,000 |
Housing |
Completed |
Wish Park |
£100,000 |
Section 106 |
Completed |
Woodingdean Central |
£150,000 |
City Parks Capital & Housing |
Completed |
Woollards Field |
£65,000 |
Section 106 |
Completed |
Total |
£3,107,500 |
|
|
|
Table 2: approved work to be completed |
||||||||
|
Site |
Spend |
Funded by |
Status |
|||||
|
Package 1 |
||||||||
|
Gatton Park #1 (Redhill) |
£5,000 |
Section 106 |
Implementation in 2024/25 |
|||||
|
Newhaven Street |
£5,000 |
Housing |
Implementation in 2024/25 |
|||||
|
The Level Play Area |
£50,000 |
City Parks |
Implementation in 2024/25 |
|||||
|
Package 2 |
||||||||
|
Happy Valley |
£60,000 |
City Parks |
Implementation in 2024/25 |
|||||
|
Hove Lagoon |
£58,994 |
Section 106 |
Implementation in 2024/25 |
|||||
|
Mackie Park |
£45,000 |
City Parks |
Implementation in 2024/25 |
|||||
|
Ovingdean |
£30,000 |
Section 106 |
Implementation in 2024/25 |
|||||
|
William Clark |
£50,000 |
Section 106 & City Parks |
Implementation in 2024/25 |
|||||
|
Package 3 |
||||||||
|
Hollingbury Park |
£120,000 |
City Parks |
Implementation in 2024/25 |
|||||
|
Manor Road |
£40,000 |
Section 106 |
Implementation in 2024/25 |
|||||
|
Stanmer Heights |
£15,000 |
Housing |
Implementation in 2024/25 |
|||||
|
Wolseley Road |
£50,000 |
Housing |
Implementation in 2024/25 |
|||||
|
Package 4 |
||||||||
|
Kingswood Flats |
£25,000 |
Housing |
Implementation in 2024/25 |
|||||
|
Mile Oak Recreation |
£150,000 |
Section 106 & Housing |
Implementation in 2024/25 |
|||||
|
Milner Flats Play Area |
£50,000 |
Housing |
Implementation in 2024/25 |
|||||
|
Total |
£753,994 |
|
|
|||||
|
|
|
|
|
|||||
Table 3: projects for approval |
|||||||||
Site |
Estimated Spend |
Work Required |
Funding Source |
Section 106 |
External Funding |
Status |
|||
Hove Park Play Area (Phase 2) |
£210,204 |
Refurbishment |
Section 106 |
£210,204 |
|
Procurement 2024/25 |
|||
Preston Park Outdoor Fitness Area |
£86,100 |
New provision |
Section 106 |
£86,100 |
|
Procurement 2024/25 |
|||
Preston Park Wheelchair Swing |
£52,500 |
New provision |
Section 106 |
£52,500 |
|
Procurement 2024/25 |
|||
Queens Park Play Area (Phase 2) |
£148,265 |
Refurbishment |
Section 106 |
£148,265 |
|
Procurement 2024/25 |
|||
Saltdean Multi Use Games Area (MUGA) |
£130,789 |
Refurbishment |
Section 106 & Community Funding |
£113,789 |
£17,000 |
Procurement 2024/25 |
|||
Stanmer Park Accessible Play Area and Trail |
£671,172 |
Refurbishment / New Provision |
Section 106 |
£671,172 |
|
Procurement 2024/25 |
|||
Victoria Recreation Ground/Park |
£71,526 |
New provision |
Section 106 |
£71,526. |
|
Procurement 2024/25 |
|||
Wild Park Play Area for older children / young adults |
£229,485 |
New Provision |
Section 106 |
£229,485 |
|
Procurement 2024/25 |
|||
Wish Park Outdoor Fitness Area |
£91,000 |
New provision |
Section 106 & Grant Funding |
£21,000 |
£70,000 |
Procurement 2024/25 |
|||
Total |
£1,691,041 |
|
|
£1,604,042 |
£87,000 |
|
|||